Project/ElectricalWorks: Difference between revisions

m
1 revision imported
imported>Jmf
m (1 revision imported)
 
(9 intermediate revisions by 2 users not shown)
Line 24:
* Replace failing sockets on Workshop pillars
* Balance power phases - move load off L3 onto L1 & L2
* Replace NVR switch on bandsaw - difficult to switch off
* Install dedicated circuit for door reader
 
== Completed Projects ==
Line 56 ⟶ 58:
* [[Project/ElectricalWorks/DB3aRework|Rebuild board DB3A; provide power for new planer thicknesser]]
* Replaced broken socket in kitchen
* Investigate building power monitor and re-instate
* Install fused spur for the [[tools/aircleaner|Air Cleaner]]. Remove chained extension leads.
* Replace damaged socket on east wall. Switch welded closed due to overload.
 
== Reference Information ==
Line 197 ⟶ 202:
| 10 || MCB || 6A || B || 6K || BG || Kitchen Lights
|}
 
== Notes ==
[[File:Switch contacts.jpg|left|400px|thumb|Welded socket contacts]]
 
[[Category:Projects]]