== Planned Projects ==
* [[Project/ElectricalWorks/MainRoomRefit|Main Room re-work project - Power for the west wall, and the 3d printers]]
* Fit new overhead lighting for the kitchen table
* Main Room re-work project - Power for the west wall, and the 3d printers
* Test and sort out the emergency lighting
* Install new emergency lighting for the Laser Room and back stairs
Line 19 ⟶ 18:
* Tidy up the data rack
* Put in a fused outlet for the Workshop air cleaner
* Document the different distribution boards
* Install worklight for the wood lathe
* Install extractor fan for the Workshop
* Connect up extractor fan in toilet
* Move upstairs lights onto the Kitchen board
* Replace failing sockets on Workshop pillars
* Balance power phases - move load off L3 onto L1 & L2
* Replace NVR switch on bandsaw - difficult to switch off
* Install dedicated circuit for door reader
 
== Completed Projects ==
Line 49 ⟶ 51:
* Install frost protection heaters in both toilets
* Install fused outlet in Workshop for the auto dust extractor on the bandsaw
* Document the different distribution boards
* Fit new overhead lighting for the kitchen table
* Fit lighting socket above stairs for feature lighting
* Replaced failed e-stop contactor in Main Workshop. Fix e-stop / keyswitch contention problem.
* Install additional double socket in Laser Room for new leather sewing machine
* [[Project/ElectricalWorks/DB3aRework|Rebuild board DB3A; provide power for new planer thicknesser]]
* Replaced broken socket in kitchen
* Investigate building power monitor and re-instate
* Install fused spur for the [[tools/aircleaner|Air Cleaner]]. Remove chained extension leads.
* Replace damaged socket on east wall. Switch welded closed due to overload.
 
== Reference Information ==
Line 56 ⟶ 68:
File:Isolator.jpg|Isolation switch
File:Zone23board.jpg|Main 3-phase board - Main supplies for the lab
File:Detail_main_board.jpg|Main electrical panelboard
File:DB1A.jpg|Single phase sub-board DB1A - emergency stop circuits in the Workshop
File:Detail_db1a.jpg|Board DB1A
Line 62 ⟶ 74:
File:Detail_db2a.jpg|Board DB2A
File:DB3A.jpg|3-phase sub-board DB3A - Workshop tools
File:Detail_db3a.jpg|Board DB3A
File:Estopsystem.jpg|Workshop emergency stop contactor and reset switch
File:E-stop_01.jpg|Emergency stop contactor
File:E-stop_02.jpg|Emergency stop contactor detail
File:E-stop_reset.jpg|Emergency stop reset switch
File:3phaseoutlets.jpg|3-phase socketssocket
File:Emon_tx.jpg|Energy Monitor transmitter
File:Test_switches.jpg|Emergency Lighting test switches
File:Detail_kitchen.jpg|Kitchen Board
</gallery>
 
A fish key for the emergency lighting switches is kept in the upstairs distribution board cupboard in the kitchen.
 
=== Distribution Board Schedules ===
 
<big>'''This schedule is accurate as of 18/06/2021'''</big>
 
{|class="wikitable"
|+ Main Distribution Board, Merlin Gerin 3-phase, 63A / 30mA RCD
|-
!Notes !! Make !! Icn !! Curve !! Rating !! Type !! colspan="2" | Circuit !! Type !! Rating !! Curve !! Icn !! Make !! Notes
|-
|- style="background-color:#ffcccc;"
| style="background-color:#ffcccc;" | Lobby Lights || style="background-color:#ffcccc;" | Merlin Gerin || style="background-color:#ffcccc;" | 10K || style="background-color:#ffcccc;" | B || style="background-color:#ffcccc;" | 6A || style="background-color:#ffcccc;" | MCB || style="background-color:#ffcccc;" | 1L1 || rowspan="3" | 4 || rowspan="3" | MCB || rowspan="3" | 32A || rowspan="3" | C || rowspan="3" | 10K || rowspan="3" | Schneider || rowspan="3" | 3-phase,
| 1L1 || MCB || 6A || B || 10K || Merlin Gerin || Lobbby Lights
Feed for DB3A
|- style="background-color:#f0f0a0;"
| 1L2Loading Bay Lights || MCBMerlin Gerin || 10A10K || B || 10K10A || Merlin GerinMCB || Loading Bay Lights1L2
|- style="background-color:#a0ccff;"
| 1L3Mezzanine Lights (Laser Rm) || MCBMerlin Gerin || 6A10K || B || 10K6A || Merlin GerinMCB || Mezanine Lights (Laser Room)1L3
|-
|- style="background-color:#ffcccc;"
| style="background-color:#ffcccc;" | Toilet Heaters || style="background-color:#ffcccc;" | Merlin Gerin || style="background-color:#ffcccc;" | 10K || style="background-color:#ffcccc;" | C || style="background-color:#ffcccc;" | 10A || style="background-color:#ffcccc;" | MCB || style="background-color:#ffcccc;" | 2L1 || rowspan="3" | 5 || rowspan="3" | MCB || rowspan="3" | 20A || rowspan="3" | B || rowspan="3" | 10K || rowspan="3" | Merlin Gerin || rowspan="3" | 3-phase, Metal Lathe
| 2L1 || MCB || 10A || C || 10K || Merlin Gerin || Toilet Frost protection heaters
|- style="background-color:#f0f0a0;"
| 2L2Kitchen Sockets || MCBMerlin Gerin || 20A10K || B || 10K20A || Merlin GerinMCB || Unknown2L2
|- style="background-color:#a0ccff;"
| 2L3Data Rack || MCBMerlin Gerin || 15A10K || B || 10K15A || Merlin GerinMCB || Data Rack2L3
|- style="background-color:#ffcccc;"
| Not Fitted || || || || || || 3L1 || 6L1 || MCB || 10A || B || 10K || NotMerlin Gerin || Workshop fittedLights
|- style="background-color:#f0f0a0;"
| Fire Alarm || Merlin Gerin || 10K || B || 15A || MCB || 3L2 || 6L2 || MCB || 15A32A || B || 10K6K || Merlin Gerin || FireMain AlarmRoom Sockets
|- style="background-color:#a0ccff;"
| E-stop Loop || Merlin Gerin || 10K || B || 16A || MCB || 3L3 || 6L3 || MCB || 16A50A || B || 10K || Merlin Gerin || EmergencyFeed Stopto LoopDB1A, Workshop sockets
|- style="background-color:#ff70ff;"
| 4 || MCB || 15A || B || 6K || Merlin Gerin || 3-phase, Feed for DB3A, Drill Press & Grinder
|- style="background-color:#ff70ff;"
| 5 || MCB || 20A || B || 10K || Merlin Gerin || 3-phase, Metal Lathe
|- style="background-color:#ffcccc;"
| 6L1 || MCB || 10A || B || 10K || Merlin Gerin || Workshop Lights
|- style="background-color:#f0f0a0;"
| 6L2 || MCB || 32A || B || 6K || Merlin Gerin || Main Room Sockets
|- style="background-color:#a0ccff;"
| 6L3 || MCB || 50A || B || 10K || Merlin Gerin || Feed to DB1A, Workshop sockets
|}
 
Line 120 ⟶ 131:
 
{|class="wikitable"
|+ Distribution Board DB2A, MK Single Phase, 100A. Dual 30mA RCD board. Fed from L3 phase directly.
|-
!Circuit !! Type !! Rating !! Curve !! Icn !! Make !! Notes
Line 126 ⟶ 137:
| 1 || MCB || 40A || B || 6K || MK || Water Heater
|- style="background-color:#ccffcc;"
| 2 || MCB || 16A || B || 6K || MK || NotEnergy usedMonitor socket
|- style="background-color:#ccffcc;"
| 3 || MCB || 20A || C || 6K10K || Chint || Upstairs heatpump
|- style="background-color:#ccffcc;"
| 4 || MCB || 32A || B || 6K || MK || Not used
Line 136 ⟶ 147:
| 6 || MCB || 50A || B || 6K || MK || Feed for Kitchen board
|- style="background-color:#ffcccc;"
| 7 || MCB || 16A || C || 6K10K || Chint || Kitchen and Workshop heat pumps
|- style="background-color:#ffcccc;"
| 8 || MCB || 16A || B || 6K || MK || Not used
Line 143 ⟶ 154:
|- style="background-color:#ffcccc;"
| 10 || MCB || 6A || B || 6K || MK || Not used
|}
 
'''Distribution Board DB3A'''
 
32A 3-phase panel, connected via an emergency stop contactor.
The metal lathe has a junction in here as well.
 
{|class="wikitable"
|+ Distribution Board DB3A, Three Phase, 32A. On E-stop circuit
|-
!Circuit !! Type !! Rating !! Curve !! Icn !! Make !! Notes
|-
| 1 || 30mA 3-phase RCBO || 16A || C || 6K || MCG || Pillar Drill
|-
| 2 || 30mA 3-phase RCBO || 16A || C || 6K || MCG || Pedestal Grinder
|- style="background-color:#ffcccc;"
| 3 || 30mA RCBO || 16A || C || 6K || MCG || West Pillar 16A socket
|- style="background-color:#ffccccf0f0a0;"
| 4 || 30mA RCBO || 16A || C || 6K || MCG || East Pillar 16A socket
|- style="background-color:#ff70ffa0ccff;"
| 5 || 30mA RCBO || 16A || C || 6K || MCG ||
|}
 
Line 170 ⟶ 202:
| 10 || MCB || 6A || B || 6K || BG || Kitchen Lights
|}
 